Thu 18 Oct 2012, 16:54 GMT

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Mount Asahi vessel. CSSC delivers LNG dual-fuel bulker to Eastern Pacific nearly four months early  

210,000-tonne Mount Asahi handed over ahead of contract schedule.

Mount Vision vessel. New Times Shipbuilding delivers three LNG dual-fuel tankers in four days  

Chinese yard hands over one VLCC and two Aframax-size crude tankers within a single week.

Mercedes Pinto vessel TTS LNG bunkering. Baleària ferry completes LNG bunkering at regular berth in Las Palmas for first time  

LNG refuelling of Mercedes Pinto set to take place weekly without changing berth.

Baltic Timber vessel. Baltic Shipping Company takes delivery of wind-assisted hybrid coaster  

3,550-dwt vessel is fitted with Econowind VentoFoils and a battery package.

Pakistan flag. Vitol Bunkers launches first commercial bunkering service at Gwadar Port  

Company begins offering HSFO, VLSFO and LSMGO at the Pakistani deepwater port.

Port of Singapore. Trailing 3-month bunker sales fall to lowest since April 2025 in Singapore  

Bunker volume of 13.569m tonnes sold between April and June was worst result in 14 months.

Glander International Bunkering logo. Glander International Bunkering reports $23.4m pre-tax earnings amid volatile shipping markets  

Bunker trading company says new fuels volumes doubled over the past year, driven by client demand.

Aerial view of tanker vessel at sea. ISO-compliant fuels increasingly causing operational problems, Lloyd’s Register warns  

Latest FOBAS report finds fuel quality risk shifting beyond off-specification fuels.

Bioethanol bunkering at the Port of Santos. Bunker One completes Latin America’s first bioethanol bunkering of a deep-sea container vessel  

500,000-litre delivery at Santos marks a first for bioethanol as a marine fuel.

Maritime Technologies Forum (MTF) logo. MTF issues safety management guidelines for methanol-fuelled ships  

New MTF report offers recommendations for developing and strengthening safety management systems for methanol as a fuel.