Thu 18 Oct 2012 16:54

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Christian Vandvig Finnerup, Dan-Bunkering. Dan-Bunkering appoints Christian Vandvig Finnerup as US managing director  

Finnerup transitions from Singapore role to lead American operations.

Hai Gang Wei Lai vessel. SIPG orders Wärtsilä systems for new LNG bunker vessel  

Shanghai International Port Group orders integrated cargo handling and fuel systems from Wärtsilä.

Chris Seide, Integr8 Fuels and William Kanavan, Pentarch Offshore Solutions. Integr8 Fuels signs MOU with Pentarch for bunker services at Port of Edrom  

Integr8 Fuels and Pentarch Offshore Solutions have signed an agreement to develop bunker fuel services.

Eagle Vellore vessel. MISC orders two LNG dual-fuel Suezmax tankers as part of fleet renewal  

Malaysian shipowner expands dual-fuel fleet with newbuilds backed by long-term charters.

Eunice Low, Oilmar DMCC. Oilmar DMCC appoints Eunice Low as marine fuels trader in Singapore  

Low joins firm's Singapore trading department with a decade of industry experience.

HMM container ship. HD Hyundai secures $1.46bn order for eight LNG dual-fuel container ships  

South Korean shipbuilder reports highest container ship order volume since 2007 supercycle.

Arctic black carbon emissions urgency graphic. Clean Arctic Alliance urges IMO action on black carbon after 'disappointing' COP30  

Environmental coalition calls for Arctic shipping fuel regulations ahead of December 5 deadline.

Egypt's Ministry of Petroleum and Mineral Resources and Suez Canal Authority MOU Signing Ceremony. Egypt's petroleum ministry and Suez Canal Authority sign MOU for LNG bunkering facility  

Ministry and canal authority to develop LNG supply station in Port Said.

Legend of the Seas main engine startup. Meyer Turku starts first main engine on Legend of the Seas cruise ship  

Finnish shipbuilder fires up Wärtsilä engine ahead of 2025 Royal Caribbean delivery.

Malik Energy Leadership Development Programme group photo. Malik Energy launches internal leadership development programme  

Marine fuel supplier rolls out training initiative for managers across its supply and energy divisions.





 Recommended