Thu 18 Oct 2012, 16:54 GMT

Singapore LNG terminal nearing completion


City-state's first LNG facilility on Jurong Island is said to be close to completion.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be close to completion.

In its latest update on the construction project, SLNG said that the terminal facility was 95 percent completed and that there had been good progress on LNG Tanks 1 & 2, where hydrotesting had been carried out and the temporary wall openings closed.

Installation of the perlite insulation between the inner and outer wall of Tank 1 has started. On Tank 3, erection of the inner nickel steel tank wall is 50 percent completed.

Progress is also said to have been made on the sea water intake; the major civil works have been completed, equipment installed and the sheet piles removed to allow erection of the sea water filters.

Piping works are expected to be completed by the end of October and equipment installation is reaching completion. Electrical/ instrumentation cable pulling and termination works are said to be well underway.

According to SLNG, progress on the Secondary Berth have reached 33 percent, with piling for the tertiary jetty completed. The main quay wall and its tie-back system have been installed and dredging of the secondary berth area is underway.

EPC contractor Samsung C&T has increased the site workforce to approximately 2,800 staff. To date, more than 9 million hours have been worked on the LNG Terminal project without any lost time injury, SLNG said.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business, i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


DP World London vessel. DP World names first methanol dual-fuel vessel at ceremony in Aarhus  

Marine services business, Shipping Solutions, names 1,250-TEU boxship with five-cylinder main engine.

Wind of Ocean vessel. LD Armateurs launches first of two SOVs for Vattenfall at Chinese shipyard  

Wind of Ocean features hybrid-electric propulsion and a double-ended hull design.

Business handshake. Singapore and Brazil sign MoU to establish green and digital shipping corridor  

Two countries will collaborate on maritime decarbonisation, digitalisation and alternative marine fuel supply chains.

WinGD logo. WinGD modelling shows retrofit pathways to net zero can pay off, but policy support remains key  

Fuel economics and regulation — not engine technology — are the main barriers to cost-effective decarbonisation retrofits, says report.

We are hiring graphic. Arte Bunkering seeks Mandarin-speaking senior bunker trader to establish presence in China  

European trading firm is expanding into China with its first on-the-ground hire.

Empire State Building, New York. Monjasa recruiting trader for New York team  

Experience in marine fuel or shipping an advantage but not a requirement.

Maritime Bunkering course participants. SSA launches training course to prepare maritime companies for Singapore’s mandatory digital bunkering  

Course designed to help companies evaluate the impact of digitalisation on their existing workflows and business processes.

Limassol cityscape. Monjasa opens two trader roles at Cyprus base, one for Italian speaker  

Experience in shipping or sales described as a requirement.

GRSE work order handing-over ceremony. GRSE wins West Bengal orders for two hybrid diesel-electric ferries  

Indian state-owned shipbuilder expands green inland waterway portfolio with latest contracts.

New Sea Generation (NSG) logo. New Sea Generation seeks experienced bunker traders in Greece  

Bunker trading firm is offering equity and a path to partnership.