Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


Spirit of Toulouse vessel. Norsepower installs first rotor sail aboard methanol-powered ro-ro vessel built for Airbus charter  

The Spirit of Toulouse will carry six rotor sails alongside dual-fuel methanol engines on a transatlantic route.

Mercedes Pinto truck-to-ship (TTS) bunkering at S.C. de Tenerife. Baleària Canarias completes first truck-to-ship LNG bunkering for fast ferry at Tenerife  

Mercedes Pinto received around 600 MWh of LNG via two tanker trucks simultaneously.

O Bunkering logo. O Bunkering claims 15-minute marine lubricant delivery at Duqm  

Omani supplier says local stock enables rapid turnaround for vessel operators.

Shenghang Yongle vessel. World's first operational ammonia bunker vessel enters service  

Converted 5,500-cbm gas carrier has received the first ammonia bunkering class certificate.

Philippos Ioulianou, EmissionLink. Shipowners risk financial exposure by delaying EU allowance transfers, EmissionLink warns  

EmissionLink says last-minute EUA compliance habits are creating avoidable financial and commercial risk.

Vinssen and WE Tech Solutions MoU signing. South Korea’s Vinssen signs MoU with Finland’s WE Tech Solutions to target European marine electrification market  

The agreement combines hydrogen fuel cell systems with advanced power conversion and management technology.

Steel cutting ceremony of vessel with builder's hull no. CHB2053. Changhong International starts building 21,700-TEU LNG dual-fuel container ship for MSC  

Vessel is described as the largest container ship currently under construction in Zhejiang Province.

MSC Leticia X naming and delivery ceremony. Changhong International delivers fifth MSC LNG dual-fuel boxship 324 days early  

Chinese shipyard hands over 10,300-TEU vessel to MSC well ahead of contract schedule.

Chang Ping Yuan vessel. Cosco Shipping names 88,000-cbm VLGC Chang Ping Yuan with dual-fuel LPG propulsion  

Owner claims 20% CO₂ reduction and Panama Canal compatibility across both lock systems.

World Fuel logo. World Fuel seeks senior marine fuels sales executive in London  

Position requires minimum of 10 years' experience in marine fuels, marine energy, or shipping.