Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


VPS logo. Fuel quality management for vessels in extended idle: Arabian Gulf, Gulf of Oman and adjacent anchorages | Rahul Choudhuri, VPS  

Managing fuel quality deterioration following the closure of the Strait of Hormuz.

Person signing a document. Agastya Green Fuels signs 250,000 t/yr e-methanol offtake deal with Sri Lanka’s SAR Group  

Indian producer and Sri Lankan maritime firm agree long-term green methanol supply partnership.

Bunker Holding logo. Bunker Holding seeks risk specialist for Copenhagen internal pricing desk  

Danish bunker group is expanding its internal pricing team to meet growing demand for fixed-price solutions.

Global biofuels demand chart. Biofuel demand could surge 70% by 2030 as food price fears mount  

T&E warns governments risk trading an oil crisis for a food crisis as biofuel targets strain vegetable oil and fertiliser markets.

Shore power illustration. Shore power shifts from voluntary measure to compliance requirement, DNV white paper finds  

Shore power is moving from an optional emissions tool to a regulatory obligation for shipowners in key trades.

Giosuè Vezzuto and Ahmed Eldemerdash. Baker Hughes’ NovaLT 16 gas turbine receives RINA type approval for marine propulsion on hydrogen and natural gas  

Certification covers operation on natural gas and blends up to 100% hydrogen for marine use.

AiP award ceremony for nuclear reactor integration in cargo vessel design. ABS grants approval in principle for nuclear reactor integration in cargo vessel design  

ABS, HD KSOE, Capital Maritime Group and MIT have received approval in principle for a nuclear-powered cargo vessel propulsion system.

Green e-fuel export corridor consortium partners logos. Green e-fuel export corridor between Brazil and Belgium advances to feasibility stage  

A consortium has been formed to develop a green e-fuel corridor linking Porto do Açu to Antwerp-Bruges.

Naming ceremony of Ocean Express and Ocean Navigator vessels. Sallaum Lines takes delivery of two LNG-fuelled PCTCs in simultaneous handover ceremony  

RoRo carrier receives MV Ocean Express and MV Ocean Navigator from Chinese shipyard.

Person signing a document. Agastya Group signs MoU with Andhra Pradesh government for 1 MTPA green methanol hub at Mulapeta Port  

India-based Agastya Group plans a $6.5bn green methanol export facility on the country's east coast.