Mon 24 Sep 2012, 08:11 GMT

LNG terminal project ahead of schedule


LNG facilility is said to be on course to be ready for operational start up by the second quarter of 2013.



Singapore LNG Corporation's (SLNG) project to build the country's first LNG terminal on Jurong Island is said to be proceeding ahead of schedule.

In a recent update on the construction project, SLNG said that the terminal facility was almost 92 percent completed and that there has been steady progress on LNG Tanks 1 & 2, where hydrotesting has already started.

Equipment installation and piping erection is well advanced and cable pulling is ongoing. The sea water intake concrete structure is completed and removal of the coffer dam is underway to allow mechanical works to start, SLNG said.

Progress on the third LNG tank [pictured] continues ahead of schedule and Secondary Berth piling works for both jetties and quay wall are said to be progressing well.

The Singapore LNG Terminal project has exceeded 7.5 million man hours safely worked on the overall project without any lost time injury since the start of the project in February 2010.

SLNG said it is well placed to complete the LNG Terminal, ready for operational start up by the second quarter of 2013.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3), which is being constructed by Samsung C&T Corporation (Samsung) as part of the LNG Terminal EPC contract.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

Image: Third LNG tank at SLNG's terminal on Jurong Island.


AuctionConnect and Asyad Shipping logos. Asyad Shipping adopts AuctionConnect digital bunker platform under three-year deal  

Middle East shipping company to implement auction-based procurement system across fleet operations.

Fuel for thought: LNG for Cruise report cover. LNG remains the most deployable decarbonisation option for cruise shipping, Lloyd’s Register report finds  

Classification society’s latest research examines the fuel’s role in the sector’s energy transition and pathway to net zero.

Dr. Ibrahim Muritala, ABS. ABS engineer to discuss performance-based hydrogen framework at SPE symposium  

Dr Ibrahim Muritala to join panel examining shift from colour-based hydrogen labelling to carbon intensity metrics.

Cosco Shipping Peony vessel. Cosco Shipping completes methanol dual-fuel retrofits on four ultra-large container vessels  

Chinese shipping line retrofits 20,000-teu and 13,800-teu vessels with methanol propulsion systems.

BW Lesmes alongside Levante LNG vessel. BW LNG vessel completes first gassing-up operation with bunker barge  

BW Lesmes transitions from drydock to cargo readiness using an LNG bunker barge.

Mark Bell, SGMF. LNG marine fuel shows up to 29% emissions reduction in new SGMF study  

Latest life cycle assessment shows improved methane slip control, with well-to-wake reductions of up to 25%.

Michelle McDade, Global Fuel Supply. Blue Energy Partners appoints Michelle McDade as head of operations  

McDade brings more than eight years of bunkering experience to the Oslo-based role.

Person signing a document. Venture Energy signs green methanol supply deal with Shenji Energy  

Hong Kong-based firm to purchase ISCC EU-certified biomass-derived methanol for shipping clients.

Steel cutting ceremony of vessel with builder's hull no. CHB2060. Changhong International begins construction on second 11,400-teu LNG dual-fuel container ship  

Chinese shipbuilder starts work on vessel CHB2060, second of 18-ship series for Oceanroutes.

Keel-laying ceremony of Celsius. Keel laid for LNG bunkering vessel Celsius  

Turkish shipbuilder begins construction of dual-fuel bunkering vessel for Sirius Shipping and Gasum.