Tue 9 Aug 2011 09:46

LNG bunkering factored into berth project


Singapore construction project to allow for potential future LNG bunkering opportunities.



Singapore LNG Corporation Pte. Ltd. (SLNG) has awarded the engineering, procurement, and construction (EPC) contract for the secondary berth of its LNG Terminal on Jurong Island.

About the Secondary Berth Project

The Secondary Berth Project, covering approximately 10 hectares of reclaimed land adjacent to the LNG Terminal site, forms part of the S$1.7 billion overall Singapore LNG Terminal project cost and comprises:

(1) a secondary jetty designed to berth LNG ships with a cargo capacity ranging from 60,000 to 265,000 cubic metres (m3), and

(2) a tertiary jetty marine sub-structure designed for the future berthing of smaller LNG ships and barges with cargo capacity ranging from 10,000 to 40,000 m3.

These two new jetties are in addition to the primary jetty (cargo capacity of 120,000 to 265,000 m3) which is being constructed by Samsung C&T Corporation (Samsung) as part of the current LNG Terminal EPC contract.

Secondary Berth Project Adds Potential to Develop Other Services of the LNG Terminal

"Overall the Secondary Berth Project adds flexibility and value to the range of LNG Terminal services that SLNG can offer its customers in Singapore and regionally. This is totally consistent with our goal of becoming a gas hub for the region," explained Mr Neil McGregor, SLNG’s Chief Executive Officer.

“We have a masterplan with built-in options to the LNG Terminal that will facilitate the majority of LNG market scenarios that are likely to develop in the region,” added McGregor.

The secondary jetty has space provision for the future installation of loading arms and associated piping for the unloading of refrigerated Liquefied Petroleum Gas (LPG) ships with cargo capacity range of 60,000 to 80,000 m3. This will facilitate the future import of LPG (a substitute of naptha) as a feedstock for Singapore’s four ethylene crackers, when the market requires it.

The secondary jetty will allow for the development of an LNG break bulk business i.e the unloading of LNG from larger ships for later reloading onto smaller ships able to access markets where port facilities cannot handle larger LNG ships; and also allows for the reloading of smaller LNG vessels to facilitate prospective future regional LNG redistribution, and potentially future LNG bunkering opportunities. According to SLNG, these are options that, if not allowed for now, would be extremely difficult to retrofit in the future.

“With its additional berthing capacity, the Secondary Jetty will improve the resilience of the LNG Terminal and enable Singapore to import more LNG when required. This will add to EMA’s efforts to enhance Singapore’s energy security and diversify our natural gas supplies.” said Chee Hong Tat, Chief Executive, Energy Market Authority.

Award of the EPC Contract for Secondary Berth Project

The tender was keenly contested by four tenderers and some novel design alternatives were received as part of the tender process. After a rigorous and robust selection process, SLNG awarded the EPC contract to Samsung for an undisclosed sum. Apart from putting forward the most competitive and lowest priced tender, Samsung's design and engineering proposal was found to provide the best quality and to deliver the best value to SLNG. McGregor commented: "There are some synergistic benefits to having Samsung as a single contractor across both sites. However, the award was made on merit, considering each tender as a standalone proposal."

“Samsung is very pleased to be awarded the Secondary Berth Project by SLNG. Our success in this tender demonstrates Samsung’s continued commitment to making Singapore’s LNG Terminal a reality. We are confident of delivering both the LNG Terminal and Secondary Berth projects safely and within schedule,” said Paul Shin, Vice President & Head of South East Asia of Samsung C&T Corporation.

Main LNG Terminal on Track

The EPC work on the Secondary Berth will take approximately 29 months and is expected to begin in late August 2011 and targeted for completion in December 2013. The main LNG Terminal project is progressing well and is fast approaching 50 percent overall completion. Over two million man hours have been worked on site to date without lost time injury. Final commissioning of the LNG Terminal is expected to be completed on schedule for commercial operations to commence by second quarter of 2013.


Christian Vandvig Finnerup, Dan-Bunkering. Dan-Bunkering appoints Christian Vandvig Finnerup as US managing director  

Finnerup transitions from Singapore role to lead American operations.

Hai Gang Wei Lai vessel. SIPG orders Wärtsilä systems for new LNG bunker vessel  

Shanghai International Port Group orders integrated cargo handling and fuel systems from Wärtsilä.

Chris Seide, Integr8 Fuels and William Kanavan, Pentarch Offshore Solutions. Integr8 Fuels signs MOU with Pentarch for bunker services at Port of Edrom  

Integr8 Fuels and Pentarch Offshore Solutions have signed an agreement to develop bunker fuel services.

Eagle Vellore vessel. MISC orders two LNG dual-fuel Suezmax tankers as part of fleet renewal  

Malaysian shipowner expands dual-fuel fleet with newbuilds backed by long-term charters.

Eunice Low, Oilmar DMCC. Oilmar DMCC appoints Eunice Low as marine fuels trader in Singapore  

Low joins firm's Singapore trading department with a decade of industry experience.

HMM container ship. HD Hyundai secures $1.46bn order for eight LNG dual-fuel container ships  

South Korean shipbuilder reports highest container ship order volume since 2007 supercycle.

Arctic black carbon emissions urgency graphic. Clean Arctic Alliance urges IMO action on black carbon after 'disappointing' COP30  

Environmental coalition calls for Arctic shipping fuel regulations ahead of December 5 deadline.

Egypt's Ministry of Petroleum and Mineral Resources and Suez Canal Authority MOU Signing Ceremony. Egypt's petroleum ministry and Suez Canal Authority sign MOU for LNG bunkering facility  

Ministry and canal authority to develop LNG supply station in Port Said.

Legend of the Seas main engine startup. Meyer Turku starts first main engine on Legend of the Seas cruise ship  

Finnish shipbuilder fires up Wärtsilä engine ahead of 2025 Royal Caribbean delivery.

Malik Energy Leadership Development Programme group photo. Malik Energy launches internal leadership development programme  

Marine fuel supplier rolls out training initiative for managers across its supply and energy divisions.