Thu 22 Jun 2017, 09:45 GMT

Gard highlights mass flow meter 'discrepancies'


P&I club issues recommendations to ensure bunker barge operator compliance.



Source: Gard

Protection and indemnity (P&I) insurer Gard aims to address in this article the issues faced by members when taking bunkers in Singapore following the mandatory implementation of mass flow meters (MFM) for bunker suppliers. The introduction of mandatory use of MFMs was intended to address frequent quantity disputes arising between the bunker barge and the receiving vessel, although issues remain.

Causes of the discrepancies

There have been two main causes of the discrepancies when using the mass flow meter;

- Operational practices by the bunker barge operators, and

- Limitations of the equipment itself.

Operational practices

Gard has received reports indicating that some bunker barges were found to syphon fuel back to their tanks via pipe connections between the flow meter and the outlet flange going to the ship manifold. In such circumstances the MFM reading will be higher than the amount actually received by the ship's bunker tanks.

The Maritime Port Authority of Singapore is currently investigating these issues and has suspended several barges from operations until completion of the investigation. It is worth noting that an MPA-certified bunker barge should have all connections between the flow meter and the shipside blanked off and sealed as part of the certification.

Limitations of the MFMs

Some vessels have recently reported quantity difference exceeding their past experience. Some bunker surveyors have studies the discrepancy between the MFM readings and the vessel received figures for a duration of time. Out of 24 cases of discrepancies over the duration, the maximum discrepancy was 57.24 MT and minimum 6.79 MT. The average discrepancy, in the disputed cases, was approximately 19 MT.

These discrepancies can be due to:

- Errors in the tank calibration tables for the receiving vessel.

- Errors in the MFM's measurement of the flow rate.

Any errors in the tank calibration of the vessel would be consistent with or without the MFM. To identify this issue a vessel experience factor (VEF) from her previous bunkering operations should be taken into account.

Errors in the MFM reading can also account for such discrepancies. All MFMs have a maximum and minimum flow rate, commonly known as 'Qmax' and 'Qmin' respectively. These limits define the operational accuracy within which the system is qualified to operate. In other words, if the flow rate of the liquid is outside these limits, the calibration of the equipment may not be accurate. It is seldom that the flow rate exceeds the Qmax, as it is usually about 1,000 t/h (forward flow). However, during stripping of the bunker barge's tanks, the flow rate can frequently fall below the Qmin. The longer the duration of the stripping, the more likelihood of a discrepancy between the MFM and the ship's received figures.

Additionally, MFM parameters such as Damping, Drive Gain, Low Flow Cut Off Value & Air Index can affect the accuracy of measurement if they exceed the manufacturers' recommended limits during the bunkering operation.

While stripping of the bunker tanks is allowed under the TR48 (Technical Reference For Bunker Mass Flow Metering), it has been noted that prolonged stripping operations causes frequent fluctuations in the flow rate with several instances of the flow rate falling below the Qmin. It has also been observed that some bunker barges conduct stripping operations in the middle of bunkering which is not permitted under TR48 and can lead to measurement uncertainty.

Recommendations

To ensure that bunker barge operators comply with all the necessary requirements, Gard recommends the following;

1. Compare the certificate of the MFM with the actual equipment fitted on the barge (comparing the serial number) to verify that the certificate is for the equipment actually fitted.

2. Seal checks: there are a number of seals, up to 20 in some cases, fitted on the MFM and other piping on the barge. These seals have to be checked and verified before every delivery.

3. The bunker surveyors should inspect the barge piping, especially around the manifold areas for any drain lines, fittings or stub pieces from where bunker oil may be tapped back into the barge tanks. If any such fittings are found, the surveyors are instructed to seal any valves leading to such fittings and report the vessel's chief engineer to the Maritime Port Authority of Singapore. The surveyor should also ensure that the Meter Totalizer Log is available for inspection as required under TR48.

4. Meter Zero should be the last thing that is done before commencing the bunker delivery and must always be done AFTER the hose has been fitted to the ship's manifold.

5. Where the bunker surveyor has been engaged, the survey report should indicate an evaluation of the meter profile in order to ensure that the basic MFM profile parameters (Qmin, Damping, Drive Gain, Low Flow Cut Off Value & Air Index) are within operating limits.

6. If there is significant discrepancy between the vessel received figures and the MFM figures after having physically verified all the above points, the following actions are recommended:

7. Repeat steps 2 and 3 as stated above.

8. Inform the MPA following the guidelines on 'Mass Flow Meter Dispute Management'

9. Engage an MFM advisor to study the meter profile in detail. This will involve the MFM profile ASCII files, Transmitter Configuration Report etc. The surveyor should also be asked to provide an independent opinion on the validity of the delivered quantity.

In addition to the physical checks, members and clients could consider incorporating protective clauses in their bunker purchase contracts. The protective clauses could include the provision of the need to physically check the bunker quantities on the delivery barge before and after bunkering.


Peter Keller, SEA-LNG. UK P&I Club joins SEA-LNG coalition to support LNG marine fuel adoption  

Insurer brings 50 years of LNG experience to methane pathway coalition focused on maritime decarbonisation.

FCM LNG fuel supply system render. Alfa Laval launches LNG fuel supply system with cryogenic technology  

Swedish firm unveils FCM LNG system for LNG-powered vessels, with marine deliveries planned for 2027.

Union Maritime's chemical tankers with Anemoi Rotor Sails. Union Maritime orders Anemoi rotor sails for two chemical tanker newbuilds  

Wind propulsion technology to help shipowner exceed IMO 2030 greenhouse gas reduction targets.

Iona vessel. Lloyd's Register completes Europe's first major LNG cruise ship dry docks with Carnival  

Iona and Mardi Gras projects required 18 months of planning and in-service passenger inspections.

Anglo-Eastern's ammonia pilot training course. Anglo-Eastern completes pilot training course for ammonia-fuelled vessels  

Ship manager prepares crew ahead of first ammonia-fuelled vessel takeover with inaugural training programme.

Burando Atlantic Group 2025 sustainability report cover. Burando Atlantic publishes first sustainability report, secures ISCC EU recertification  

Maritime group releases inaugural sustainability report while Burando Energies extends biofuel traceability certification.

Conceptual illustration of high-power marine fuel cell unit. ABB and HDF Energy to develop high-power fuel cells for large ships  

Joint development targets megawatt-scale hydrogen fuel cell units for container feeders and liquefied hydrogen carriers.

Chart showing Singapore TTM bunker sales, Aug '22 - Nov '25. Singapore bunker sales break new ground as TTM volumes surpass 56m tonnes  

Trailing 12-month bunker sales rise to new all-time record at Asian port.

Bow Leopard vessel. Odfjell launches operational green corridor between Brazil and Europe using biofuel  

Chemical tanker operator establishes route using B24 sustainable biofuel without subsidies or government support.

United LNG I vessel. Somtrans christens 8,000-cbm LNG bunker barge for Belgian and Dutch ports  

United LNG I designed for inland waterways and coastal operations up to Zeebrugge.